How do you connect an offshore wind farm to the energy network?
The task of constructing and operating grid connections for offshore wind farms is performed by our affiliated company transpower offshore gmbh. On behalf of transpower stromübertragungs gmbh, it performs the planning and construction of connection lines at sea up to the grid junction point. The projects mainly involve the following tasks:
- Development of technical concepts for connecting the offshore wind farms
- Continuation or new development of route planning
- Carrying out the legal approval and nature conservation procedures for realisation of the grid connections.
- Putting out to tender, awarding and processing grid connection projects for offshore wind farms

1. Crossing Norderney
Before the grid operator was required by law to create a grid connection for the offshore wind farm, the wind farm developers planned possible routes themselves.
Right from the beginning, one possibility was crossing the island of Norderney. At first, the individual wind farm developers planned for 14 individual routes. This solution would not have been technically possible and also not efficient.
When the task was taken over by transpower (formerly E.ON Netz), grid connections were bundled.
These lines cross Norderney on the way from the sea to the land. For this purpose, the so-called hollow ducting construction was built in spring 2005 at a total length of 1.5 kilometres through which the cable connection for the wind farms was to be drawn. The first cabling for the alpha ventus connection was drawn through this subterranean ducting at the end of May 2008. With the exception of horizontal boring, no more excavation work is necessary on Norderney for connecting the future wind farms.
2. Project BorWin1
The first project that involves direct current technology was the grid connection for the BARD Offshore 1 wind farm. The project name is based on the Borkum 2 wind farm cluster and is called BorWin1. A transformer station was provided by transpower on a platform for transporting the wind energy to land. From there, the electricity produced by the wind power plants will be transformed into direct current, and conveyed through the sea and then overland by what is known as a high voltage direct current (HVDC) transmission system to the nearest network supply entry point, a transformer station. Direct current is particularly suitable when long distances have to be covered and large amounts of electricity transmitted. For the connection of offshore wind farms to the network, both are the case.
The transformer station will transform the DC energy into alternating current and feed it into the grid
Several kilometres of cable were already laid in 2008 for the grid connection on shore. The rest of the total of 200 kilometres followed in 2009 from the high seas around the island of Norderney down to the substation at Diele near Papenburg. This long stretch is the longest connection in the world to be built for a grid connection for an offshore wind farm. In order to carry out the construction of a high voltage DC transmission line with a capacity of 400 MW, transpower (formerly E.ON Netz) contracted the company, ABB (also see the ABB-Website).
The land route from Hilgenriedersiel to Diele is around 75 kilometres long. In May 2008, E.ON Netz started working on the northern part of the land ducting connection from Hilgenriedersiel to the Diele substation. Almost 38 kilometres of cable were laid up to the A31 road. In the summer of 2008, eight subterranean horizontal bores were made with a total length of 742 metres under the dunes and dykes of Norderney and by Hilgenriedersiel for the passage of the first direct current cable. To protect the Lower Saxony Wadden Sea National Park, the cable was passed through these subterranean bores and offshore cable was connected to the onshore cable. In autumn 2008 a length of 1,330 meters passed under the Ems. The second part of the onshore cable connection to the transformer station followed in 2009. Around 125 kilometres of cable was also laid through the tidal flats and offshore in the summer and fall of 2009. The connection to the voltage transformation substation platform of BARD is also upcoming.
The technical installations carried out by transpower in the voltage transformation substation in Diele were also more or less completed at the end of November 2009. Test and trial operation was started successively. There the direct current will then again be transformed into three-phase alternating current and fed into the 380 kilovolt grid.
The final start-up of the grid connection will first take place following the erection of the wind park in the spring/summer of 2010. A high-performance grid connection via the world's longest direct current connection between an offshore wind park and the extra high voltage grid can then be used to feed large amounts of wind energy into the power grid.
3. Project alpha ventus
Some offshore wind farms that are quite close to the coast can be connected by means of individual cable connections that are laid through the sea to the nearest network supply entry point.
The first wind farm for which transpower realised such a grid connection is "alpha ventus". The offshore test field is 45 kilometres from the coast of Borkum and is a joint venture between E.ON Climate & Renewables, EWE and Vattenfall Europe New Energy.
Already in 2007, four subterranean horizontal bores were carried out under the dunes and in the mudflats in front of Norderney for the alpha ventus connection. In the spring of 2008, a 1.5-kilometre long hollow ducting structure was completed across Norderney. Simultaneously, the new substation at Hagermarsch was erected to which alpha ventus was connected.
At the end of May 2008, the cabling was laid for the connection from alpha ventus to the hollow ducting construction. In summer 2008, both the onshore as well as the offshore cables were laid.
As one can imagine, the laying of cable in the North Sea places very different demands on technology and equipment compared to laying land-bound cabling into cable trenches. Cables to the wind farm weighing many tonnes – and many kilometres in length – must be aligned and laid on schedule, whilst taking the characteristics of the sea bed into account using varied procedures.
Special ships are required to transport the pre-rolled cable on large rotating disks and unroll them into the sea. There are only a few of these special ships and one example is the Giulio Verne: the ship can transport up to 7,000 tonnes of cable, it is 128.5 metres long and 35 metres wide. As a comparison, a normal football field in Germany is 68 by 105 metres.
The grid connection went into operation in May 2009.
4. Other Projects
transpower is also preparing further grid connections for offshore wind parks with the BorWin2, DolWin1, HelWin1 and SylWin1 projects. To this purpose, converter stations in Dörpen and Büttel are planned as additional points of delivery. Necessary planning determination processes for the lines leading from offshore to the respective point of delivery are also already in progress.
In the summer of 2010, transpower will carry out seven horizontal drilling procedures offshore in preparation for BorWin2 on Norderney and on the mainland, into which the cables for the grid connection will be placed in the subsequent course of the project. At the same time, all preparations for the converter stations offshore and on land, as well as for the laying of buried and undersea cable, are being made in order to be able to provide additional grid connections in a timely fashion.

